IMPSA WIND

1,5 e 3,0 MW windmill, towers and blades production.
300 windmills of 1.5 MW / year

Developed designs / services:
Site selection
Masterplan design
Teams coordination
Architecture design
Landscape design
Irrigation system
Concrete structure design
Foundations
Steel structure design
Electricity  installations
Voice, data and image on IP web system
Water and sewage systems
Sewage processing station
Air conditioning system
Paving and drainage design
Prevention and Fire Fighting system
Exhaustion system
Compressed air system
Signalling design
Projects approval
Environmental licencing
Construction advisement

Project characteristics:

Place:

Suape. Pernambuco / Brazil.

Land area:

266,970.39m²

Constructed area:

17,190.10m² (primeira etapa)

Concret Structure:

6,677 m³

Steel structure:

450 t

Piles:

362 piles of +/- 10 m

Bridge Crane:

Yes (up to 140 t)

Eletricity system:

2 MVA

Sewage processing station:

72.5 m³/day anaerobic system

 

imagem 1
Perspective:
industrial buildings (first step)

imagem 2
Briefing air

imagem 3
Dressingroom, leisure  and restaurant buildings

imagem04
Windmill production building


Windmill production building, looking to the oven.


Windmill and Nacelles production buildings


Windmill production building


Windmill production building